What is Focus in Capacity Template

The Focus is basically a value to determine the amount of work the resource will be doing in a sprint.

For eg if Focus is 0.5 and capacity is 8 hrs per day, then it is assumed that the resource will spend 8 * 0.5 = 4 hrs per day in the sprint.

By default, Focus value is set to 1.