Hours (Time Tracking)

...

Total Capacity : The capacity in number of hours for the user defined in the Capacity Template for that particular sprint duration

...

Time Spent : The sum of all the time spent entered in all the issues assigned to the user in that sprint

Remaining Capacity : Total Capacity - Time SpentCapacity per day * remaining days in Sprint

Remaining Work : The sum of the remaining Estimates of all the issues assigned to the user in that sprint

Story Points

...

Total Capacity : The capacity in story points for the user defined in the Capacity Template for that particular sprint duration

Allocated Work : The sum of the Story Points of all the issues assigned to the user in that sprint

Remaining Capacity : Total Capacity - Time SpentCapacity per day * remaining days in Sprint

Expected Progress : No of Story Points that should have been completed till date

...