Progress Calculation based on Remaining Estimate :
Progress percentage is percentage of ‘Time Spent' (Time Tracking) out of the total 'Time Spent’ + 'Remaining Estimate'. For example, if
Time Spent = 3h
Remaining Estimate = 12h
Progress = (3 / (3+12) )*100 = 20%
Progress Calculation based on Original Estimate :
Progress percentage is percentage of 'Time Spent' (Time Tracking) out of the total 'Original Estimate'. For example, if
Time Spent = 4h
Original Estimate = 8h
Progress = (4 / 8)*100 = 50%
...