As per above parameters, the app scans through all the issues in the Sprint and which issues are assigned to each resource. For each issue
Time Spent and Original Estimates values are taken into consideration.
Original Estimate value is used for Allocated Capacity for the assigned resource.
For eg Issue 1 in the Sprint
Original Estimate = 8hrs
Assigned resource = User 1
Then Allocated Capacity = 8hrs for User 1
The app then calculates the total duration for the sprint, the time spent by each resource on the assigned issues and checks the attached capacity template to calculate the allocated hours and remaining capacity.